Power Department of Sikkim OR Sikkim Power Department
PHYSICAL PROGRESS OF HEPs ALLOTED TO IPPs
Name of ProjectDeveloperDam/Barrage/IntakeHead Race Tunnel/AditsSurge ShaftPressure Shaft/PenStockPower HouseTail RaceTransmission/Evacuation SystemsRemarks
Teesta Stage-IIITeesta Urja Limited       Five Units (5x200 MW) commissioned and synchronised and all units (6 nos) declared commissioned on 17 Feb 2017.
Teesta Stage-IVNHPC LtdNot StartedNot StartedNot StartedNot StartedNot StartedNot StartedNot StartedYet to start. No activities started at site. Public hearing under way.
Teesta-VNHPC Ltd       Commissioned on 2008.
Teesta Stage-VILanco Energy Pvt LtdUnder constructionUnder constructionUnder ConstructionUnder constructionExcavation works completedUnder constructionYet to startWork stopped due to financial issues. Project under SDR. 51% promoter equity offloaded to ICICI Bank (Lead Lender).
Panan HEPHimagiri Hydro Energy Pvt LtdYet to startYet to startYet to startYet to startYet to startYet to startYet to startOnly preliminary construction works started. National Wild Life Board Clearance not obtained. As per their progress report NOV 2016 expected COD 2021. Has directed the developer to submit the financial credibility to complete the project.
Rongnichu HEPMadhya Bharati Power CorporationUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionYet to startProject under construction and cumulative progress of the project till date is 37%
Chuzachen HEPGati Infrastructures Ltd       Commissioned on June 2013.
Bhasmey HEPGati Infrastructures LtdUnder constructionUnder constructionUnder constructionYet to startUnder constructionYet to startYet to startUnder construction and cumulative progress of the project till date is around 36%. Developer has been directed to expedite the construction activities at site on all fronts.
Rangit-II HEPSikkim Hydro Ventures LtdUnder constructionUnder constructionYet to startYet to startYet to startYet to startYet to startProject under construction and cumulative progress of the project till date is 30%. Has requested for extension of COD to DEC 2019.
Rangit-IV HEPJal Power Corporation LtdUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionYet to startWorks stopped due to financial issues. Project under SDR.
Dikchu HEPSneha Kinetic Power Projects LtdUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionCompletedCommissioned on 31st April 2017.
Jorethang Loop HEPDANS Energy Pvt Ltd       Commissioned on SEP 2015.
Lachung HEPLachung Hydro Power Pvt. LtdYet to startYet to startYet to startYet to startYet to startYet to startYet to startNo progress achieved. Has directed the developer to submit the latest progress report based on revised time frame failing which termination/cancellation of MOU/IA will be initiated.
Bhimkyong HEPTeesta Hydro Power Pvt. LtdYet to startYet to startYet to startYet to startYet to startYet to startYet to startNo progress achieved. Has directed the developer to submit the latest progress report based on revised time frame failing which termination/cancellation of MOU/IA will be initiated.
Bop HEPChungthang Hydro Power Pvt. LtdYet to startYet to startYet to startYet to startYet to startYet to startYet to startNo progress achieved. Has directed the developer to submit the latest progress report based on revised time frame failing which termination/cancellation of MOU/IA will be initiated.
Tashiding HEPShiga Energy Pvt. LtdUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionUnder constructionProject under construction and cumulative progress of the project till date is around 98%. Expected COD April 2017.
Rahi Kyoung HEPSikkim Engineering Pvt LtdYet to startYet to startYet to startYet to startYet to startYet to startYet to startProject under survey & investigation. DPR is under preparation. Public hearing has been concluded by SPCB.
Rangit-III HEPNHPC Limited       Commissioned on 2003.
Rateychu-BakchachuSamvijay Power and Allied Industries Ltd.       Finalization of MOU under process by utilising the discharge of Bakchachu (river) only and by keeping Ratey Chu catchment untouched as Ratey Chu being the primary source of drinking water of Gangtok and surrounding area.